Highway 400 - Resurfacing of Select Northbound Lanes
Federal contribution
$1.1M
$1,100,000
Federal share50%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2010
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Jun 23, 2010(actual)
- Construction end
- Sep 17, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2010
- Construction end6 months earlyforecast Mar 31, 2011
Also in Severn
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39636 in the federal list. How to read these figures.