Washago Washroom Rehabilitation
Federal contribution
$79,683
Federal share80%
of $99.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Severn
- Construction start
- Jun 3, 2021(actual)
- Construction end
- Jan 10, 2022(actual)
Against the original forecast
- Construction end6 weeks lateforecast Nov 30, 2021