Hale and Trafalgar Street Overpass - London
Federal contribution
$3.8M
$3,816,338
Federal share33%
of $11.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- Feb 22, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Apr 1, 2010
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30894 in the federal list. How to read these figures.