Hale and Trafalgar Street Overpass - London

London, Ontario

completeHighways and RoadsISF
Federal contribution
$3.8M
$3,816,338
Federal share33%

of $11.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of London
Construction start
Feb 22, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Apr 1, 2010

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30894 in the federal list. How to read these figures.