Durham Street Reconstruction
Federal contribution
$116,666
Federal share33%
of $350.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Cramahe
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Sep 29, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 15, 2010
- Construction end4 weeks lateforecast Aug 30, 2010
Also in Cramahe