Durham Street Reconstruction

Cramahe, Ontario

completeHighways and RoadsISF
Federal contribution
$116,666
Federal share33%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Cramahe
Construction start
Jun 1, 2010(actual)
Construction end
Sep 29, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 15, 2010
  • Construction end4 weeks lateforecast Aug 30, 2010