Environmental Assessment, Engineering and Design of a Gravity Sewer Extension
Federal contribution
$33,927
Federal share23%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2017
201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Cramahe
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start8 months lateforecast Mar 1, 2017
- Construction end3 months lateforecast Sep 30, 2019
Also in Cramahe