Back to projects

Keeler Centre Facility and Grounds Accessibility Upgrades

Cramahe, Ontario

underwayRecreationCCRIS
Federal contribution
$121,440
Federal share40%

of $303.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 29, 2022
today
202220232024202520262027
BuiltForecast

Approved 9 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Township of Cramahe
Construction start
Jul 2, 2024(actual)
Construction end
Nov 27, 2026(forecast)

Also in Cramahe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60781 in the federal list. How to read these figures.