Upgrading Municipal Sidewalk Infrastucture
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Cramahe
- Construction start
- Aug 21, 2021(actual)
- Construction end
- Oct 31, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 2, 2021
- Construction end4 weeks lateforecast Oct 1, 2021
Also in Cramahe
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59612 in the federal list. How to read these figures.