Schedule

Announced and approvedJun 15, 2021
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Cramahe
Construction start
Aug 21, 2021(actual)
Construction end
Oct 31, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 2, 2021
  • Construction end4 weeks lateforecast Oct 1, 2021