Back to projects

Walnut/Kensington Area Sanitary and Storm Sewer Replacement

London, Ontario

completeWastewaterISF
Federal contribution
$284,406
Federal share32%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of London
Construction start
Apr 19, 2010(actual)
Construction end
Mar 31, 2011(actual)

Also in London