Bathurst Street Sanitary Sewer Replacement
Federal contribution
$400,105
Federal share29%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- Apr 12, 2010(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast May 1, 2010
- Construction end4 months earlyforecast Mar 31, 2011
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31209 in the federal list. How to read these figures.