Old South Storm Sewer and Sanitary Sewer
Federal contribution
$929,319
Federal share29%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- Mar 22, 2010(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start6 weeks earlyforecast May 1, 2010
- Construction end4 months earlyforecast Mar 31, 2011