Glencoe Fire Hall Replacement
Federal contribution
$333,333
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Southwest Middlesex
- Construction start
- May 31, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 30, 2009
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Southwest Middlesex
- Renovations to Glencoe Memorial Arena$1.1M
- Glencoe Main Street Watermain Reconstruction$781.4K
- Melbourne Water Tower Exterior and Interior Upgrades$148.6K
- Wardsville Wastewater Treatment Plant and System Improvements on Queen Street and Talbot Street$106.9K
- Rehabilitation of Municipal Office Roof & HVAC$99.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31230 in the federal list. How to read these figures.