Back to projects

Rehabilitation of Municipal Office Roof & HVAC

Southwest Middlesex, Ontario

completeVentilationCVRIS
Federal contribution
$99,479
Federal share80%

of $124.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 15, 2022(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction end3 months lateforecast Oct 1, 2022

Also in Southwest Middlesex