Wardsville Wastewater Treatment Plant and System Improvements on Queen Street and Talbot Street

Southwest Middlesex, Ontario

completeWastewaterCWWF
Federal contribution
$106,938
Federal share50%

of $213.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2017
201820192020
Built

Approved 7 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 7, 2017(actual)
Construction end
Dec 1, 2019(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Apr 1, 2017