Glencoe Main Street Watermain Reconstruction
Federal contribution
$781,440
Federal share40%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 5, 2021
20212022
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Southwest Middlesex
- Construction start
- Jul 8, 2021(actual)
- Construction end
- Apr 13, 2022(actual)
Against the original forecast
- Construction end7 weeks earlyforecast May 30, 2022
Also in Southwest Middlesex
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57282 in the federal list. How to read these figures.