Back to projects

Rosslyn Library Addition

Oliver Paipoonge, Ontario

completeCultureISF
Federal contribution
$100,000
Federal share33%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 28, 2009(actual)
Construction end
Mar 12, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 7, 2009
  • Construction end3 weeks earlyforecast Mar 31, 2010

Also in Oliver Paipoonge