Back to projects

Rehabilitation of Oliver Paipoonge Fire Halls

Oliver Paipoonge, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$78,287
Federal share80%

of $97.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 15, 2021(actual)
Construction end
Sep 14, 2023(actual)

Against the original forecast

  • Construction end2 months lateforecast Jun 30, 2023

Also in Oliver Paipoonge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59453 in the federal list. How to read these figures.