Rehabilitation of Oliver Paipoonge Fire Halls
Federal contribution
$78,287
Federal share80%
of $97.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Oliver Paipoonge
- Construction start
- May 15, 2021(actual)
- Construction end
- Sep 14, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Jun 30, 2023
Also in Oliver Paipoonge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59453 in the federal list. How to read these figures.