Water System Rehabilitation and Modernization

Oliver Paipoonge, Ontario

completeDrinking WaterCWWF
Federal contribution
$50,000
Federal share24%

of $207.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 8, 2019
20182019
Built

Approved 10 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 23, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 21, 2017
  • Construction end4 weeks earlyforecast Oct 31, 2018