Water System Rehabilitation and Modernization
Federal contribution
$50,000
Federal share24%
of $207.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 8, 2019
20182019
Built
Approved 10 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Oliver Paipoonge
- Construction start
- Oct 23, 2017(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 21, 2017
- Construction end4 weeks earlyforecast Oct 31, 2018
Also in Oliver Paipoonge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51870 in the federal list. How to read these figures.