Back to projects

Kakabeka Fire Station

Oliver Paipoonge, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$104,000
Federal share33%

of $312.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 14, 2009(actual)
Construction end
Mar 10, 2010(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Mar 31, 2010

Also in Oliver Paipoonge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31375 in the federal list. How to read these figures.