completeHighways and RoadsISF
Federal contribution
$44,050
Federal share32%

of $138.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 18, 2009(actual)
Construction end
Sep 30, 2009(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 1, 2009