Sewage Pumping Station Upgrades
Federal contribution
$26,216
Federal share12%
of $225.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Westport
- Construction start
- Sep 15, 2010(actual)
- Construction end
- Oct 15, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 1, 2010
- Construction end2 weeks earlyforecast Oct 31, 2011