Dunbar Heights Sidewalk Rehabilitation
Federal contribution
$46,154
Federal share33%
of $138.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Atikokan
- Construction start
- Jul 13, 2009(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 1, 2009
Also in Atikokan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32402 in the federal list. How to read these figures.