Wastewater treatment plant upgrades

Plessisville, Quebec

completeWastewaterCC
Federal contribution
$140,901
Federal share23%

of $601.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 13, 2009
2010
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Plessisville
Construction start
Sep 28, 2009(actual)
Construction end
Oct 22, 2010(actual)

Against the original forecast

  • Construction end7 months lateforecast Mar 31, 2010

Also in Plessisville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32703 in the federal list. How to read these figures.