Goodwill Social Enterprise Abilities Centre

London, Ontario

completeRecreationISF
Federal contribution
$3.9M
$3,898,151
Federal share33%

of $11.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Goodwill Industries
Construction start
May 1, 2010(actual)
Construction end
Aug 18, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Oct 15, 2009
  • Construction end7 weeks lateforecast Jun 30, 2011