Hutton House Main Building Expansion

London, Ontario

completeOtherISF
Federal contribution
$256,250
Federal share33%

of $768.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Aug 25, 2010(actual)
Construction end
Aug 30, 2011(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Sep 30, 2011