Back to projects

The Grand Theatre Rehabilitation

London, Ontario

completeCultureISF
Federal contribution
$919,792
Federal share33%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
The Grand Theatre
Construction start
May 17, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 30, 2009
  • Construction end3 months earlyforecast Mar 31, 2011

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33398 in the federal list. How to read these figures.