Multi-Sport/Activity Indoor Centre

London, Ontario

completeRecreationISF
Federal contribution
$1.2M
$1,164,042
Federal share29%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Sep 7, 2010(actual)
Construction end
Nov 30, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 2, 2010
  • Construction end4 weeks lateforecast Oct 31, 2011