Heelan Street Sewer Repairs
Federal contribution
$106,919
Federal share32%
of $331.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- Sep 28, 2009(actual)
- Construction end
- Aug 30, 2010(actual)
Against the original forecast
- Construction end4 weeks lateforecast Jul 31, 2010