Roundabout Construction
Federal contribution
$51,000
Federal share20%
of $255.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- District of Tofino
- Construction start
- Jan 24, 2011(actual)
- Construction end
- Oct 30, 2011(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Feb 22, 2011
- Construction end2 weeks lateforecast Oct 15, 2011
Also in Tofino
- Secondary Wastewater Treatment and System Upgrades$22.0M
- Tofino - Secondary Wastewater Treatment and System Upgrades Phase 2$9.0M
- Clayoquot Sound Biosphere Centre$7.2M
- Pacific IPCA Innovation Centre Deep-Energy Retrofit, Net-Zero Energy Strategy, and Accessibility Upgrade$4.7M
- District of Tofino Wastewater Treatment Plant$875.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35324 in the federal list. How to read these figures.