Wastewater Upgrade
Federal contribution
$81,960
Federal share33%
of $245.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- District of Logan Lake
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Mar 19, 2010(actual)
Also in Logan Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35487 in the federal list. How to read these figures.