Water Distribution System Improvements

Logan Lake, British Columbia

completeDrinking WaterCWWF
Federal contribution
$875,000
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Logan Lake
Construction start
Nov 27, 2017(actual)
Construction end
Sep 28, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Nov 1, 2017
  • Construction end4 weeks lateforecast Aug 31, 2018

Also in Logan Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49843 in the federal list. How to read these figures.