Water Distribution System Improvements
Federal contribution
$875,000
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- District of Logan Lake
- Construction start
- Nov 27, 2017(actual)
- Construction end
- Sep 28, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Nov 1, 2017
- Construction end4 weeks lateforecast Aug 31, 2018