Logan Lake - Logan Lake Recreation Centre - Ice Plant Replacement
Federal contribution
$250,950
Federal share20%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
20232024
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- District of Logan Lake
- Construction start
- Apr 24, 2023(actual)
- Construction end
- Sep 24, 2024(actual)
Against the original forecast
- Construction start4 weeks lateforecast Mar 24, 2023
- Construction end3 months earlyforecast Dec 18, 2024
Also in Logan Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61433 in the federal list. How to read these figures.