Back to projects

Renewal/Rehabilitation of Existing Infrastructure

Logan Lake, British Columbia

completeDrinking WaterSCF
Federal contribution
$225,000
Federal share33%

of $675.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2015
201620172018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
District of Logan Lake
Construction start
Jun 15, 2017(actual)
Construction end
Sep 4, 2018(actual)

Against the original forecast

  • Construction start20 months lateforecast Oct 1, 2015
  • Construction end7 months lateforecast Jan 31, 2018

Also in Logan Lake