Domestic Water Metering - Stage 1
Lake Cowichan, British Columbia
Federal contribution
$200,000
Federal share26%
of $760.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Lake Cowichan
- Construction start
- Nov 10, 2009(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2009
- Construction end6 months earlyforecast Dec 31, 2010
Also in Lake Cowichan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35494 in the federal list. How to read these figures.