Cowichan Valley - Mesachie Lake Fire Hall Retrofit

Lake Cowichan, British Columbia

completeVentilationCVRIS
Federal contribution
$279,718
Federal share80%

of $349.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 17, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 1, 2023(actual)
Construction end
Jun 30, 2023(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jan 17, 2023
  • Construction end4 months lateforecast Mar 1, 2023

Also in Lake Cowichan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60399 in the federal list. How to read these figures.