Back to projects

Lake Cowichan - Flood Protection Sewage Lift Station No. 1

Lake Cowichan, British Columbia

completeWastewaterCC
Federal contribution
$76,733
Federal share33%

of $230.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 9, 2010
2011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Lake Cowichan
Construction start
Feb 23, 2011(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jan 4, 2011
  • Construction end6 weeks lateforecast Feb 18, 2011

Also in Lake Cowichan