Lake Cowichan Water Main Upgrades
Lake Cowichan, British Columbia
Federal contribution
$680,177
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Lake Cowichan
- Construction start
- Jun 5, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2017
- Construction end12 months earlyforecast Mar 31, 2020
Also in Lake Cowichan