Energy Efficiency Improvements

Nelson, British Columbia

completeGreen EnergyISF
Federal contribution
$187,500
Federal share24%

of $780.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 8, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Nelson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35536 in the federal list. How to read these figures.