Energy Efficiency Improvements
Federal contribution
$187,500
Federal share24%
of $780.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional District of Central Kootenay
- Construction start
- Jun 8, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Nelson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35536 in the federal list. How to read these figures.