Arena Upgrades - Fraser Lake
Federal contribution
$146,972
Federal share33%
of $440.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Fraser Lake
- Construction start
- May 11, 2009(actual)
- Construction end
- Sep 15, 2009(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Sep 30, 2009