Fraser Lake Active Transportation Community Plan

Fraser Lake, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share95%

of $52.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2022
2023
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Village of Fraser Lake
Construction start
Aug 31, 2022(actual)
Construction end
Oct 27, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 23, 2022
  • Construction end10 months lateforecast Dec 30, 2022