Fraser Lake - Wastewater Lagoon Expansion
Federal contribution
$889,613
Federal share60%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Fraser Lake
- Construction start
- Jul 13, 2020(actual)
- Construction end
- Oct 13, 2021(actual)
Against the original forecast
- Construction start6 months lateforecast Jan 1, 2020
- Construction end2 months earlyforecast Dec 19, 2021
Also in Fraser Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56233 in the federal list. How to read these figures.