Fraser Lake Water Reservoir Replacement

Fraser Lake, British Columbia

underwayDrinking WaterGIS
Federal contribution
$1.2M
$1,190,500
Federal share40%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 31, 2023
202420252026
BuiltForecast

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Fraser Lake
Construction start
Jun 27, 2024(actual)
Construction end
Dec 17, 2025(forecast)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 12, 2024