Granthams Landing Water System Upgrade

Sunshine Coast, British Columbia

completeDrinking WaterISF
Federal contribution
$168,667
Federal share33%

of $506.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 20, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Sep 6, 2010