Square Bay Wastewater Treatment Plant Upgrade
Sunshine Coast, British Columbia
Federal contribution
$420,062
Federal share50%
of $840.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Sunshine Coast
- Construction start
- Oct 2, 2017(actual)
- Construction end
- Mar 15, 2019(actual)
Against the original forecast
- Construction start6 months earlyforecast Apr 13, 2018
- Construction end4 months lateforecast Nov 16, 2018