Square Bay Wastewater Treatment Plant Upgrade

Sunshine Coast, British Columbia

completeWastewaterCWWF
Federal contribution
$420,062
Federal share50%

of $840.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 2, 2017(actual)
Construction end
Mar 15, 2019(actual)

Against the original forecast

  • Construction start6 months earlyforecast Apr 13, 2018
  • Construction end4 months lateforecast Nov 16, 2018