Regional Water Cross Connection Control and Universal Metering Program - Phase 2
Sunshine Coast, British Columbia
Federal contribution
$1.7M
$1,723,333
Federal share33%
of $5.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
2016201720182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Regional District of Sunshine Coast
- Construction start
- Sep 19, 2016(actual)
- Construction end
- Mar 15, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 15, 2016
- Construction end16 months lateforecast Oct 31, 2017