Sunshine Coast - Langdale Wastewater Treatment System Upgrade

Sunshine Coast, British Columbia

approvedWastewaterGIS
Federal contribution
$410,199
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 15, 2023
today
20242025202620272028
BuiltForecast

Approved 8 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Mar 1, 2027(forecast)
Construction end
Oct 29, 2027(forecast)