Pender Harbour Water Systems Water Main Replacements

Sunshine Coast, British Columbia

completeDrinking WaterCWWF
Federal contribution
$1.6M
$1,650,000
Federal share50%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 22, 2018(actual)
Construction end
Dec 27, 2019(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2020