Bridge Construction in Estevan
Federal contribution
$261,673
Federal share31%
of $850.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Nov 9, 2009(actual)
- Construction end
- May 12, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Nov 23, 2009
- Construction end6 weeks lateforecast Mar 31, 2010
Also in Estevan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35936 in the federal list. How to read these figures.