Back to projects

Asphaltite Renewal Program

Thompson, Manitoba

completeHighways and RoadsISF
Federal contribution
$45,801
Federal share31%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Thompson
Construction start
Aug 13, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction end8 months earlyforecast Aug 31, 2011

Also in Thompson