Drinking Water Disinfection Upgrade
Powell River, British Columbia
Federal contribution
$2.8M
$2,825,070
Federal share33%
of $8.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Powell River
- Construction start
- Sep 6, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Dec 10, 2011