Consolidated Waste Water Treatment System
Powell River, British Columbia
Federal contribution
$2.0M
$1,999,550
Federal share50%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018201920202021
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Powell River
- Construction start
- Sep 6, 2017(actual)
- Construction end
- Mar 3, 2021(actual)
Against the original forecast
- Construction start8 months lateforecast Jan 3, 2017
- Construction end4 weeks earlyforecast Mar 31, 2021